EDS Interval Metering Upgrade
A customer may request Advanced Metering if not currently
supplied as standard metering in accordance with the terms of the Rate Schedule
under which the Customer receives electric service. Advanced Metering shall
be installed by the Company and shall be used for billing. The following fees
will apply in addition to the Energy Data Service fees.
Interval Meter Upgrade Fees¹
|
Meter
Upgrade² |
Data Collection |
| Monongahela Power - Ohio |
$572.00 |
$34.25/meter/mo |
| Monongahela Power - West Virginia |
$572.00 |
$34.25/meter/mo |
| Potomac Edison - Maryland |
$584.00 |
$35.00/meter/mo |
| Potomac Edison - Virginia |
$572.00 |
$34.30/meter/mo |
| Potomac Edison - West Virginia |
$572.00 |
$34.25/meter/mo |
| West Penn Power - Pennsylvania |
$572.00 |
$33.88/meter/mo |
1. Fees to be included as separate
line item on Customer's bill for electric service.
2. A
one-time fee will be charged along with the first month's fee.
|
|
|
|